Status: Operational since May 2006
Statistics:
Number of wind turbines: 28
Type of turbine: 2.3MW
Location of wind farm: Southwest of Elgin and 15 km west of Charleston of Aberlour
Click here for location maps.
Paul’s Hill Wind Farm is based on 28 turbine locations, a metering building, two anemometer masts and installed underground high voltage cables, temporary construction compound, access and onsite tracks and associated infrastructure (incl. grid connection).
The project construction commenced in January 2004 and the wind farm started full operation in May 2006.